HomeMy WebLinkAboutChange Order No. 3 to agreement for Evanston Water Utility SCADA Phase III Engineering Services.CITY OF EVANSTON
CHANGE ORDER
Order No. 004
Date: June 10, 2013
Agreement Date: September 29, 2009
PROJECT:
SCADA Phase III Engineering Svcs (RFP 08-74)
OWNER:
City of Evanston
ENGINEER:
CDM Smith Inc.
The following changes are hereby made to the AGREEMENT: The contract completion date is
extended to June 30, 2013.
Chanae to CONTRACT PRICE: $ 0.00
Original CONTRACT PRICE: $ 168,843.00
Current CONTRACT PRICE adjusted by previous CHANGE ORDERS $ 178,159.28
Total change in CONTRACT PRICE for this CHANGE ORDER No. 004 $ 0.00
The CONTRACT PRICE including this CHANGE ORDER will be $ 178,159.28
Original COMPLETION DATE June 30, 2011
Current COMPLETION DATE adjusted by previous CHANGE ORDERS April 30, 2013
Total Change in CONTRACT TIME for this CHANGE ORDER 153 days
The COMPLETION DATE including this CHANGE ORDER will be Sept 30, 2013
Approved by
(Owner):
City of f�Ja n Date
Accepted by (Engineer): �Inc� C/z//3