AN ORDINANCE
Authorizing the City Manager to Execute Amendments
To Air Rights Lease with Rescorp Development, Inc.
For Church Street/Chicago Avenue Project
NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF
EVANSTON, COOK COUNTY, ILLINOIS:
SECTION 1: That the amendments to the Church Street Project
Schedule of Major Dates as set forth in Exhibit A, as
part of certain leases between the City as landlord and Church Street
Associates Limited Partnership, an Illinois Limited Partnership of which
Rescorp Development, Inc., Cragin Service Corporation, Fidelity
Corporation, Holbrook Enterprises, Inc., and Liberty Lincoln Service
Corporation are the general partners and an Illinois land trust to be
formed, of which Church Street Associates Limited Partnership is the sole
beneficiary, are hereby accepted by the City Council of the City of
Evanston for the following described real property:
All that part of Lot 1 in Plat of Consolidation of the
South 12 feet of Lot 3 and all of Lots 4, 5, 6, 7, 8, 9
and 10 together with all that part of Lot 3 and Lot 3
(except the South 12 feet thereof), all in Block 14, in
• Evanston, in the East half of Section 18, Township 41
North, Range 14, East of the Third Principal Meridian,
in Cook County, Illinois,
commonly known as City of Evanston Parking Lot 28.
SECTION 2: The City Manager is hereby authorized and directed
to sign, and the City Clerk is hereby authorized
and directed to attest to the aforesaid amendments as set forth in Exhibit
A, provided, however, that the project is in compliance with all applicable
codes, including the Zoning Ordinance. The City Manager is further
authorized to negotiate any changes or additional terms and conditions with
respect to the lease of the aforesaid real property as may be deemed fit
and proper.
SECTION 3: There shall be no extension of the date for final
public garage budget approval by the City and for
the developer to furnish to the City final binding written commitments for
financing.
•
SECTION 4: City Manager and the City Clerk, respectively, are
hereby authorized and directed to execute, attest
• and deliver such other documents, agreements and certificates as may be
necessary.
•
•
Introduced: C��iLl 0 1988
Adopted: �� 1988
ATTEST./
Clerk
Approved: CCI , 1988
Mayor
Approved as to form: u�n,,/ ,
Corporation Counsel N
-2-
0
•
Church Street/Chicago Avenue Project
Schedule of -Major Dates
August 31, 1988 -
Final Public Garage budget approval date
for the City. Last day for developer to
furnish to City final binding written
commitments for financing.
November 30, 1988 -
Last date for commencement of
construction of the project (90 days
after final binding written commitment
for financing is obtained.)
August 31, 1989 -
Completion date for Public Garage
subject to extension for unavoidable
delays.
November 30, 1989 -
Latest date on which payment of minimum
rent of $130,000/year commences under
the Air Rights Lease.
March 31, 1990 -
Completion date for project subject to
extension for unavoidable delays.
May 31, 1990 -
Final completion date for the Public
Garage notwithstanding unavoidable
delays.
December 31, 1990 -
Final completion date for the project
notwithstanding unavoidable delays.
February 28, 1991 -
Latest date on which payment of minimum
rent/year commences under the Ground
Lease.
• August 31, 1988* Commencement Date of the Ground Lease
August 31, 1988* Commencement Date of the Air Rights
Lease
* or on the date of construction commencement, whichever is
earlier.