HomeMy WebLinkAboutORDINANCES-2007-002-O-07• 1 /2/2007
2-0-07
AN ORDINANCE
for the Construction of a Local Improvement known as
Evanston Special Assessment No. 1488
North of Clark Street, East of Chicago Avenue
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF
EVANSTON, ILLINOIS:
SECTION 1: That a local improvement shall be made within the City of
Evanston, County of Cook, and State of Illinois, the nature, character, locality and
description of which is as follows, to -wit:
That the unimproved public alley in the block bounded by
Sheridan Road on the north, Clark Street on the south,
Chicago Avenue on the west, and Hinman Avenue on the
• east, in the City of Evanston, be improved by excavating,
constructing the necessary drainage system and paving with
8" Portland Cement Concrete Pavement to a width of fifteen
feet (15').
SECTION 2: That the Recommendation of this Ordinance by the Board of
Local Improvements of the City of Evanston, Illinois, and the Estimate of the cost of said
improvement made by the Engineer of said Board, both hereto attached, be and the
same are hereby approved and by reference thereto made a part hereof.
SECTION 3: That said improvement shall be made and the cost thereof,
including the sum of One Hundred Ninety -Nine Thousand, Nine Hundred Thirty -Seven
and 62/100 dollars ($199,937.62), being the cost of making and collecting the
Assessment and all other expenses as provided by law, shall be paid for by Special
• Assessment in accordance with the Illinois Municipal Code, Chapter 65, Section 5/9-2-1
et seq.
2-0-07
SECTION 4: That Twenty -Nine Thousand, Five Hundred Twenty -Three •
and 32/100 dollars ($29,523.32) of the cost of said improvement shall be allocated by
the City, and One Hundred Seventy Thousand, Four Hundred Fourteen and 30/100
dollars ($170,414.30) as private benefit.
SECTION 5: That the aggregate amount to be assessed and each
individual assessment shall be divided into ten (10) installments in the manner provided
by law, and each of said installment shall bear interest at the rate of seven percent (7%)
per annum from sixty (60) days after the date of the first voucher issued on account of
work done upon said proposed improvement.
SECTION 6: That, for the purpose of anticipating the collection of the
installments of said assessment levied against the real estate benefited thereby,
general obligation bonds have been issued, fifty percent (50%) of which are payable by •
the City and fifty percent (50%) of which are payable out of said installments, bearing
interest at the rate of seven percent (7%) per annum, payable annually and signed on
behalf of the City of Evanston, Illinois, by its Mayor and attested by its City Clerk and its
corporate seal affixed thereto; and each interest coupon attached to said bonds shall
likewise be executed by and shall bear the official or facsimile signature of the same
officers who signed said bonds and who, if facsimile signatures are used, do adopt by
their execution of said bonds as and for their proper signatures their respective facsimile
signatures appearing on said coupons; and that said bonds shall be issued in
accordance with and shall be in all respects conform to the provisions of an Act of the
General Assembly of the State of Illinois, knows as the "Illinois Municipal Code",
effective July 1, 1961, and the Amendments thereto. •
—2—
2-0-07
•
•
•
SECTION 7: That David Jennings, President of the Board of Local
Improvements of the City of Evanston, Illinois, be and he is hereby directed to file a
Petition in the County Court of Cook County, Illinois, praying that steps may be taken to
levy a Special Assessment to pay the cost of said improvement in accordance with the
provisions of this Ordinance and in the manner prescribed by law.
SECTION 9: That all ordinances or parts of ordinances in conflict herewith
are hereby repealed.
SECTION 9: That this Ordinance shall be in full force and effect from and
after its passage, approval, and publication in the manner provided by law. .
Adopted by the City Council of the City of Evanston, Illinois on the 26th
day of March, 2007.
Attest:
V
Mary P. is City Clerk
f k
Approved:
R �
2007
jLor'ne H. Morton, Mayor
Aporov,od as to forts:
Herb ` rt D. Hill
FirsYAssistant Corporation Counsel
-3-
2-0-07
Recommendation •
n
�4�
n
U
•
•
SPECIAL ASSESSMENT NO. 1488
RECOMMENDATION OF THE BOARD OF LOCAL IMPROVEMENTS
TO THE CITY COUNCIL OF THE CITY OF EVANSTON, ILLINOIS
The Board of Local Improvements of the City of Evanston, Illinois,
herewith submits the draft of an Ordinance for the making of a local improvement within
the City of Evanston, County of Cook, and State of Illinois, the nature, character, locality
and description of which is as follows, to -wit:
That the unimproved public alley in the block bounded by
Sheridan Road on the north, Clark Street on the south,
Chicago Avenue on the west, and Hinman Avenue on the
east, in the City of Evanston, be improved by excavating,
constructing the necessary drainage system, and paving
with 8" Portland Cement Concrete Pavement to a width of
fifteen feet (15').
And as part of said Ordinance and in conjunction therewith, said Board also herewith
submits the plans and specifications of an estimate of the cost of said improvement,
including the cost of engineering services, as finally determined by said Board; and said
Board hereby recommends the passage of said Ordinance and the making of the
improvement described therein.
APPROVEP_/�S TO FORM:
Attorney fort eboard of Local
Improvements of the City of Evanston, Illinois
HERBERT D. HILL 24497
ELLEN SZYMANSKI 54806
ELKE B. TOBER-PURZE 40107
KENNETH R. COX 45264
BRADFORD R. YATABE 45263
CITY OF EVANSTON LAW DEPARTMENT
2100 RIDGE AVENUE
EVANSTON, ILLINOIS 60201
(847) 866-2937
Respectfully submitted,
BOARD OF LOCAL IMPROVEMENTS
CITY OF EVANSTON, ILLINOIS
By:
r - Ck " `,I
2-o'ol
ssoloste
,5~
•
ESTIMATE OF ENGINEER OF BOARD OF LOCAL IMPROVEMENTS,
• To the Board of Local Improvements of the City of Evanston:
Pursuant to a Resolution of the Board of Local Improvements of the City of Evanston, heretofore
adopted, providing that the public alley in the block bounded by Sheridan Road on the north, Clark Street on
the south, Chicago Avenue on the west, and Hinman Avenue on the east, in the City of Evanston, be improved
by excavating, improving the existing drainage system and paving with 8" Portland Cement Concrete
Pavement to a width of fifteen feet (15').
Said improvement to be constructed in detail as specified in aforesaid Resolution.
I, herewith submit an estimate of cost of such improvement as described in said Resolution, including labor,
materials, and all other lawful expenses attending the proceedings for making said improvement and the cost of
making and collecting the assessment therefore as provided by law, viz:
COST EST131ATE
ITEM
UNIT
QUANTITY
UNIT
PRICE
TOTAL
EARTH EXCAVATION
CU. YD.
200
40.00
$
8,000.00
TRENCH BACKFILL
CU. YD.
32
32.00
$
1,024.00
SUB -BASE GRANULAR MATERIAL, TYPE B
CU. YD.
10
32.00
$
320.00
GRANULAR CRADLE MATERIAL, CA-11
TON
25
32.00
$
800.00
•
AGGREGATE BASE COURSE, TYPE B, 6"
SO. YD.
325
6.00
$
1,950.00
INCIDENTAL BITUMINOUS SURFACING
TON
55
140.00
$
7,700.00
PORTLAND CEMENT CONCRETE PAVEMENT, 8"
SQ. YD.
925
55.00
$ 50,875,00
STORM SEWERS, SPECIAL, 8" (D. I. P. / CL. 50)
LIN. FT.
40
90.00
$
3,600.00
STORM SEWERS, SPECIAL, 10" (D. I. P. / CL. 50)
LIN. FT.
72
100.00
$
7,200.00
CATCHBASINS, TYPE A, 4' DIAMETER, TYPE 1 FRAME, CLOSED LID
EACH
2
3,800.00
$
7,600.00
(WITH RESTRICTOR)
MANHOLE, TYPE A, 4' DIAMETER, T)IPE 1 FRAME, CLOSED LID
EACH
2
3,500.00
$
7,000.00
INLET, TYPE A, TYPE 1 FRAME, OPEN LID
EACH
2
1,500.00
$
3,000.00
SEWER LINER INSTALLATION, 9" DIAMETER SEWER
FOOT
530
75.00
$
39,750.00
HEAVY CLEANING OF SEWER
FOOT
530
7.00
$
3,710.00
CUTTING OF PROTRUDING SERVICE CONNECTIONS
EACH
3
300.00
$
900.00
LATERAL REINSTATEMENTS, 8" DIAMETER OR LESS
EACH
15
100.00
$
1,500.00
SERVICE BYPASS SUMPS
EACH
2
500.00
$
1,000.00
ADJUSTING SANITARY SEWERS, 8" DIAMETER OR LESS
EACH
1
900.00
$
900.00
REMOVING CATCHBASINS
EACH
2
200.00
$
400.00
CONCRETE CURB, TYPE B
FOOT
110
20.00
$
2,200.00
•
PAVEMENT REMOVAL
SO. YD.
925
15.00
$
13,875.00
CURB REMOVAL
FOOT
490
5.00
$
2,450.00
DRIVEWAY PAVEMENT REMOVAL
SQ. YD.
335
15.00
$
5,025.00
BLI_EST1488
Page -2-
Estimate of Engineer of BLI — S.A. 1488 •
(Alley, N/Clark St., E/Chicago Ave.)
SIDEWALK REMOVAL
SO. FT.
450
2.00
$ 900.00
PORI-LAND CEMENTCONCRETE DRIVEWAY PAVEMENT- 8"
SO. YD.
10
40.00
$ 400.00
PORTLAND CEMENT CONCRETE SIDEWALK - 5'
SQ. FT.
400
5.00
-$ 2,000.00
PROTECTIVE SEALER
SQ. YD.
935
2.00
$ 1,870.00
CRUSHED STONE, CA -14
TON
10
40.00
$ 400.00
BITUMINOUS SURFACE REMOVAL
SO. YD.
120
10.00
$ 1,200.00
FURNISHING AND PLACING TOPSOIL, T
SO. YD.
80
5.00
$ 400.00
SODDING, SALT TOLERANT
SO. YD.
80
10.00
$ 800.00
CONSTRUCTION LAYOUT AND STAKING
SUMP
1
2,000.00
$ 2,000.00
CLOSED CIRCUITTV INSPECTION
SUMP
1
1,500.00
$ 1,500.00
DETECTABLE WARNINGS
SQ. FT.
50
10.00
$ 500.00
THERMOPLASTIC PAVEMENT MARKING LINE, 4"
FOOT
340
2.00
$ 680.00
Cost of Engineering Services ................. $ 8,254.31 •
For Lawful Expenses, etc ....................... $ 8,254.31
................................................................ $16,508.62
.RECAPITULATION
Total Cost of Construction. ..................... $183,429.00
Cost of Engineering Services .................. $ 8,254.31
For Lawful Expenses, etc . ..................... $ 8,254.31
Total Cost of Improvement ..................... $199,937.62
I hereby certify that in my opinion the above estimate does not exceed the probable cost of the above proposed
improvement and the lawful expenses attending the same.
Sat Nagar, P.E.
Senior Engineer •
Board of Local Improvements