HomeMy WebLinkAboutORDINANCES-2009-023-O-090
4/14/2009
23-0-09
AN -ORDINANCE
for the Construction of a Local Improvement. known as
Evanston Special Assessment No. 1502.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF
EVANSTON, ILLINOIS:
SECTION 1: That a local improvement shall be made within the
City of Evanston, County of Cook, and State of Illinois, the nature, character,
locality and description of which is as follows, to -wit:
That the unimproved public alley in the block bounded
by Lake Street on the north, Greenwood Street on the
• south, Grey Avenue on the west, and Brown Avenue
on the east, in the City of Evanston, be improved by
excavating, constructing the necessary drainage
system, and paving with 8" Portland Cement Concrete
Pavement, the north east -west leg to a width of
fourteen feet (14'), the south east -west leg to a width
of fourteen feet (14'), the west north -south leg to a
width of fourteen feet (14'), the east north -south leg to
a width of thirteen feet (13'), and the middle north -
south leg to a width of sixteen feet (16'),
SECTION 2: That the Recommendation (Exhibit A) of the Board of
Local Improvements of the City of Evanston, Illinois, of -this Ordinance, and the
Estimate of the Cost (Exhibit B) of said improvement made by the Engineer of
said Board, both attached hereto, be and the same are hereby approved and by
reference thereto made a part hereof.
9
23-0-09
SECTION 3: That said improvement shall be made and the cost 0
thereof, including the sum of Three Hundred Sixty -Four Thousand, Eight
Hundred Sixty -Six and 60/100 Dollars ($364,866.60), being the cost of making
and collecting the Assessment and all other expenses as provided by law, shall
be paid for by Special Assessment in accordance with the Illinois Municipal
Code, Chapter 65, Section 5/9-2-1, et seq.
SECTION 4: That One Hundred Eighty -Two Thousand, Four
Hundred Thirty -Three and 30/100 Dollars ($182,433.30) of the cost of said
improvement shall be allocated by the City, Sixty -Six Thousand, Nine Hundred
Twenty -Two Dollars ($66,922.00) as funded by a Community Development Block
Grant, and One Hundred Fifteen Thousand, Five Hundred Eleven and 30/100
Dollars ($115,511.30) as private benefit. •
SECTION 5: That the aggregate amount to be assessed and each
individual assessment shall be divided into ten (10) installments in the manner
provided by law, and each of said installment shall bear interest at the rate of
seven percent (7%) per annum from sixty (60) days after the date of the first
voucher issued on account of work done upon said proposed improvement.
SECTION 6: That, for the purpose of anticipating the collection of
the installments of said assessment levied against the real estate benefited
thereby, general obligation bonds have been issued, fifty percent (50%) of which
are payable by the City, homeowners pay thirty-one point seven percent (31.7%),
and Community Development Block Grant funds pay eighteen point three •
-2-
23-0-09
• percent (18.3%), of which are payable out of said installments, bearing interest at
the rate of seven percent (7%) per annum, payable annually and signed on
behalf of the City of Evanston, Illinois, by its Mayor and attested by its City Clerk
and its corporate seal affixed thereto; and each interest coupon attached to said
bonds shall likewise be executed by and shall bear the official or facsimile
signature of the same officers who signed said bonds and who, if facsimile
signatures are used, do adopt by their execution of said bonds as and for their
proper signatures their respective facsimile signatures appearing on said
coupons; and that said bonds shall be issued in accordance with and shall be in
all respects conform to the provisions of an Act of the General Assembly of the
State of Illinois, knows as the "Illinois Municipal Code," effective July 1, 1961, and
• the Amendments thereto.
SECTION 7: That David D. Stoneback, Interim President of the
Board of Local Improvements of the City of Evanston, Illinois, be and he is
hereby directed to file a Petition in the County Court of Cook County, Illinois,
praying that steps may be taken to levy a Special Assessment to pay the cost of
said improvement in accordance with the provisions of this ordinance and in the
manner prescribed by law.
SECTION 8: That all ordinances or parts of ordinances in conflict
herewith are hereby repealed.
•
-3-
23-0-09
SECTION 9: That this Ordinance 23-0-09 shall be in full force and •
effect from and after its passage, approval, and publication in the manner
provided by law.
w day of
Approved:
2009
Lorraine H. Morton, Mayor
Approved as to form:
Elke B. Tourze, Attorney for the
Board of Local Improvements of the
City of Evanston, Illinois
Adopted by the City Council ofwthe City of Evanston, Illinois on the
0 � , 2009.
City Clerk
•
•
IZM
23-0-09
• Exhibit A
•
•
Recommendation
-5-
0
SPECIAL ASSESSMENT NO. 1502
RECOMMENDATION OF THE BOARD OF LOCAL IMPROVEMENTS
TO THE CITY COUNCIL OF THE CITY OF EVANSTON, ILLINOIS
The Board of Local Improvements of the City of Evanston, Illinois, herewith submits the
draft of an Ordinance for the making of a local improvement within the City of Evanston,
County of Cook, and State of Illinois, the nature, character, locality and description of
which is as follows, to -wit.
That the unimproved public alley in the block. bounded by Lake Street on the
north, Greenwood Street on the south, Grey Avenue on the west, and Brown
Avenue on the east, in the City of Evanston, be improved by excavating,
constructing the necessary drainage system, and paving with 8" Portland Cement
Concrete Pavement, the north east -west leg to a width of fourteen feet (14'), the
south east -west leg to a width of fourteen feet (14'), the west north -south leg to a
width of fourteen feet (14'), the east north -south leg to a width of thirteen feet
(13'), and the middle north -south leg to a width of sixteen feet (16');
and, as part of said Ordinance, and in conjunction therewith, said Board also herewith
submits the plans and specifications of an estimate of the cost of said improvement,
including the cost of engineering services, as finally determined by said Board; and said •
Board hereby recommends the passage of said Ordinance and the making of the
improvement described therein.
APPROVED AS TO FORM:
Elke B. Toter-P�ze
Attorney for the Board of Local
Improvements of the City of Evanston, Illinois
ELKE B. TOBER-PURZE
40107
KENNETH R. COX
45264
ELIZABETH E. HOWLETT
43981
LISA K. WOODS
43999
CITY of EVANSTON LAW DEPARTMENT
2100 RIDGE AVENUE
EVANSTON, ILLINOIS 60201
(847) 866-2937
Respectfully submitted,
BOARD OF LOCAL IMPROVEMENTS
CITY OF EVANSTON, I LINOIS
t�) By: , �-) /,
/—
Davi ..D. Stoneback, Interim President
Date: April 17 , 2009
•
RESOLUTION OF THE BOARD OF LOCAL IMPROVEMENTS
Special Assessment No. 1502
• Exhibit A
•
•
Engineer's Estimate
-3-
ESTIMATE OF ENGINEER OF BOARD OF LOCAL IMPROVEMENTS •
To the Board of Local Improvements of the City of Evanston:
Pursuant to a Resolution of the Board of Local Improvements of the City of Evanston, heretofore adopted,
providing that the unimproved public alley in the block bounded by Lake Street on the north, Greenwood Street on the
south, Grey Avenue on the west, and Brown Avenue on the east, in the City of Evanston, be improved by excavating,
constructing the necessary drainage system and paving with 8" Portland Cement Concrete Pavement the North East —
West leg to a width of fourteen feet (14% the South East — West leg to a width of fourteen feet (14' ), the West North —
South leg to a width of fourteen feet ( 14' ), the East North — South leg to a width of thirteen feet (13' ), and the Middle
North — South leg to a width of sixteen feet (16').
Said improvement to be constructed in detail as specified in aforesaid Resolution.
I, herewith submit an estimate of cost of such improvement as described in said Resolution, including labor,
materials, and all other lawful expenses attending the proceedings for making said improvement and the cost of making
and collecting the assessment therefore as provided by law, viz:
COST ESTIMATE
ITEM
UNIT
ITEM
UNIT
QUANTITY
TOTAL
1
EARTH EXCAVATION
CU. YD.
555
55.00
$30,525.00
2
TRENCH BACKFILL
CU. YD.
262
20.00
$5,2
3
SUB -BASE GRANULAR MATERIAL, TYPE B
CU. YD.
10
30.00
$30 .
4
GRANULAR CRADLE MATERIAL, CA-11
TON
143
30.00
$4,290.00
5
AGGREGATE BASE COURSE, TYPE B, 4'
SQ. YD.
55
10.00
$550.00
6
INCIDENTAL HOT -MIX ASPHALT SURFACING
TON
25
150.00
$3,750.00
7
PORTLAND CEMENT CONCRETE PAVEMENT, 8"
SQ. YD.
1720
70.00
$120,400.00
8
STORM SEWERS, SPECIAL, 8" ( D. I. P. / CL 50)
FOOT
215
120.00
$25,800.00
9
STORM SEWERS, 10", TYPE 1 (R. C. P. I CL V)
FOOT
290
110.00
$31.,900.00
10
STORM SEWERS, SPECIAL, 10" (D. I. P. / CL 50)
FOOT
154
125.00
$19,250.00
11
CATCHBASINS, TYPE A, 4' DIAMETER, TYPE 1 FRAME, CLOSED LID
EACH
1
4800.00
$4,800.00
12
MANHOLE, TYPE A, 4' DIAMETER, TYPE 1 FRAME, OPEN LID
EACH
2.
4000.00
$8,000.00
13
INLET, TYPE A, TYPE 1 FRAME, OPEN LID
EACH
14
1500.00
$21,000.00
14
MANHOLE TO BE ADJUSTED
EACH
1
500.00
$500.00
15
COMBINATION CONCRETE CURB & GUTTER, TYPE B 6.12
FOOT
315
25.00
$7,875.00
16
PAVEMENT REMOVAL
SQ. YD.
40
25.00
$1,000.00
17
DRIVEWAY PAVEMENT REMOVAL
SQ. YD.
260
22.00
$5,720.00
18
COMBINATION CURB & GUTTER REMOVAL
FOOT
315
5.00
$1,575.00
19
SIDEWALK REMOVAL
SQ. FT.
1225
2.00
$2,450.00
20
PORTLAND CEMENT CONCRETE DRIVEWAY PAVEMENT - 6"
SQ. YD.
260
50.00
$13,000.00
21
PORTLAND CEMENT CONCRETE SIDEWALK - 5"
SQ. FT.
11.10
6.00
$6,6
22
PROTECTIVE SEALER
SQ. YD.
1980
2.00
$3,91$
23
CRUSHED STONE, CA - 14
TON
30
30.00
$900.00
BLI—EST 1502
•Page -2-
Estimate of Engineer of BLI - S.A. 1502
(Alley, N / Greenwood St.., E / Grey Ave.)
ITEM ITEM
NO.
24 FURNISHING AND PLACING TOPSOIL, 3"
25 SODDING, SALT TOLERANT
26 CLASS B PATCHES, SPECIAL 9" ( HES )
27 DETECTABLE WARNINGS
28 BRICK PAVING - SAND SETTING BED
29 HOT - MIX ASPHALT SURFACE REMOVAL
UNIT
UNIT
QUANTITY
TOTAL
PRICE
SQ. YD.
140
8.00
$1,120.00
SQ. YD.
140
15.00
$2,100.00
SQ. YD.
50
100.00
$5,000.00
SQ. FT.
115
25.00
$2,875.00
SQ. FT.
150
18.00
$2,700.00
SQ.. YD.
150
10.00
$1,500.00
ESTIMATED
CONSTRUCTION COST
$334,740.00
Cost of Engineering Services ................. $15,063.30
For Lawful Expenses, etc ..................... $15,063.30
.................................................... $30,126.60
• RECAPITULATION
Construction Cost............. .................. $334,740.00
Engineering .................................... $15,063.30
Legal ............................................. $15,063.30
Total Cost ....................................... $364,866.60
I hereby certify that in my opinion the above estimate does not exceed the probable cost of the above
proposed improvement and the lawful expenses attending the same.
Sat Nagar, P.E.
Senior Engineer
Board of Local Improvements
i