49-0-18
AN ORDINANCE
To Approve the Construction of a Local Improvement Known as
Evanston Special Assessment No. 1523
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF
EVANSTON, ILLINOIS:
SECTION 1: A local improvement shall be made within the City of
Evanston, County of Cook, and State of Illinois, the nature, character, locality and
description of which is as follows, to -wit:
The unimproved public alley in the block bounded on the north by Noyes
Street, on the east by Pioneer Road, on the south by Payne Street, and on the west by
McDaniel Avenue, in the City of Evanston, County of Cook, State of Illinois, be improved
by excavating, constructing the necessary drainage system and paving with 8" Portland
Cement Concrete Pavement, to a width of sixteen feet (16').
SECTION 2: The Recommendation (Exhibit A) of the Board of Local
Improvements of the City of Evanston, Illinois, of this Ordinance, and the Estimate of the
Cost (Exhibit B) of said improvement made by the Engineer of said Board, both
attached hereto, be and the same are hereby approved and by reference thereto made
a part hereof.
SECTION 3: Said improvement shall be made and the cost thereof,
including the sum of Four Hundred Eighty Thousand Four Hundred Sixty One and
10/100 Dollars ($480,461.10), being the cost of making and collecting the Assessment
49-0-18
and all other expenses as provided by law, shall be paid for by Special Assessment in
accordance with the Illinois Municipal Code, Chapter 65, Section 5/9-2-1, et seq.
SECTION 4: Two Hundred Forty Thousand Two Hundred Thirty One and
55/100 Dollars ($240,231.55) of the cost of said improvement shall be allocated by the
City; and the remainder of the cost, Two Hundred Forty Thousand Two Hundred Thirty
One and 55/100 Dollars ($240,231.55) will be allocated as private benefit.
SECTION 5: The aggregate amount to be assessed and each individual
assessment shall be divided into ten (10) installments in the manner provided by law,
and each of said installment shall bear interest at the rate of three percent (3%) per
annum from sixty (60) days after the date of the first voucher issued on account of work
done upon said proposed improvement.
SECTION 6: That, for the purpose of anticipating the collection of the
installments of said assessment levied against the real estate benefited thereby,
general obligation bonds have been issued, up to Two Hundred Forty Thousand Two
Hundred Thirty One and 55/100 Dollars ($240,231.55) of which are payable by the City,
homeowners pay up to Two Hundred Forty Thousand Two Hundred Thirty One and
55/100 Dollars ($240,231.55) of which are payable out of said installments, bearing
interest at the rate of three percent (3%) per annum, payable annually and signed on
behalf of the City of Evanston, Illinois, by its Mayor and attested by its City Clerk and its
corporate seal affixed thereto; and each interest coupon attached to said bonds shall
likewise be executed by and shall bear the official or facsimile signature of the same
officers who signed said bonds and who, if facsimile signatures are used, do adopt by
—2—
49-0-18
their execution of said bonds as and for their proper signatures their respective facsimile
signatures appearing on said coupons; and that said bonds shall be issued in
accordance with and shall be in all respects conform to the provisions of an Act of the
General Assembly of the State of Illinois, knows as the "Illinois Municipal Code,"
effective July 1, 1961, and the Amendments thereto.
SECTION 7: That David Stoneback, President of the Board of Local
Improvements of the City of Evanston, Illinois, be and he is hereby directed to file a
Petition in the Circuit Court of Cook County, Illinois, praying that steps may be taken to
levy a Special Assessment to pay the cost of said improvement in accordance with the
provisions of this ordinance and in the manner prescribed by law.
SECTION 8: All ordinances or parts of ordinances in conflict herewith are
hereby repealed.
SECTION 9: If any provision of this ordinance or application thereof to
any person or circumstance is held unconstitutional or otherwise invalid, such invalidity
shall not affect other provisions or applications of this ordinance that can be given effect
without the invalid application or provision, and each invalid application of this ordinance
is severable.
SECTION 10: The findings and recitals contained herein are declared to
be prima facie evidence of the law of the City and shall be received in evidence as
provided by the Illinois Compiled Statutes and the courts of the State of Illinois.
SECTION 11: This ordinance shall be in full force and effect from and
after its passage, approval, and publication in the manner provided by law.
—3—
49-0-18
Introduced: ��r�� , 2018 Approved:
Adopted: 12018 2018
ephe l-. Ha e yo-"
Attest: Approved as to form:
Devo� Rom, City Cl e Michelle L. Masoncup, Int4rim City
Attorney
-4-
49-0-18
Exhibit A
Recommendation
-5-
SPECIAL ASSESSMENT NO. 1523
RECOMMENDATION OF THE BOARD OF LOCAL IMPROVEMENTS
TO THE CITY COUNCIL OF THE CITY OF EVANSTON, ILLINOIS
The Board of Local Improvements of the City of Evanston, Illinois, herewith submits the
draft of Ordinance 49-0-18 for the making of a local improvement within the City of
Evanston, County of Cook, and State of Illinois, the nature, character, locality and
description of which is as follows, to -wit.
The unimproved public alley in the block bounded on the north by
Noyes Street, on the east by Pioneer Road, on the south by
Payne Street, and on the west by McDaniel Avenue, in the City of
Evanston, County of Cook, State of Illinois, be improved by
excavating, constructing the necessary drainage system and
paving with 8" Portland Cement Concrete Pavement, to a width of
sixteen feet (16).
and, as part of said Ordinance, and in conjunction therewith, said Board also herewith
submits the plans and specifications of an estimate of the cost of said improvement,
including the cost of engineering services, as finally determined by said Board; and said
Board hereby recommends the passage of Ordinance 49-0-18 and the making of the
improvement described therein.
APPROVED AS TO FORM:
Morio Treto, Jr.
Attorney for the Boar f Local
Improvements of the City of Evanston, Illinois
MICHELLE L. MASONCUP
MARIO TRETO, JR.
CITY of EVANSTON LAW DEPARTMENT
2100 RIDGE AVENUE
EVANSTON, ILLINOIS 60201
(847) 866-2937
Attorney Code 46996
Respectfully submitted,
BOARD OF LOCAL IMPROVEMENTS
CITY OF EVANST N, IL INOIS
By: YZ4�-
avid Stoneback, President
!'�
ZANZ
Date: Fe%m . t 3 , 2018
E• •
Exhibit B
Estimate
Mc
ESTIMATE OF ENGINEER OF BOARD OF LOCAL IMPROVEMENTS
To the Board of Local Improvements of the City of Evanston:
Pursuant to a Resolution of the Board of Local improvements of the City of Evanston, heretofore
adopted, providing that the unimproved public alley in the block bounded by Noyes Street on the north,
Payne Street on the south, McDaniel Avenue on the west, and Pioneer Road on the east, in the City of
Evanston, be improved by excavating, constructing the necessary drainage system and paving with 8"
Portland Cement Concrete Pavement, to a width of sixteen feet (16').
Said improvement to be constructed in detail as specified in aforesaid Resolution.
I, herewith submit an estimate of cost of such improvement as described in said Resolution,
including labor, materials, and all other lawful expenses attending the proceedings for making said
improvement and the cost of making and collecting the assessment therefore as provided by law,
COST ESTIMATE
ITEM
NO.
ITEM
UNIT
QUANTITY
PR IT
TOTAL
1
EARTH EXCAVATION
cu. YD.
484
55.00
$
26,620.00
2
TRENCH BACKFILL
CU. YD.
438
40.00
$
17,520.00
3
SUB -BASE GRANULAR MATERIAL, TYPE B
CU. YD.
40
45.00
$
1800.00
4
GRANULAR CRADLE MATERIAL, CA-11
TON
185
45.00
$
8,325.00
5
AGGREGATE BASE COURSE, TYPE 13,4'
SO. YD.
30
12.00
$
360.00
6
INCIDENTAL HOT -MIX ASPHALT SURFACING
TON
10
250.00
$
2,500.00
7
PORTLAND CEMENT CONCRETE PAVEMENT, 8'
SQ. YD.
1,615
80.00
$
129,200.00
8
STORM SEWERS, SPECIAL, 10' (D. I. P. ! CL 50)
FOOT
241
125.00
$
30,125.00
9
STORM SEWERS, IT, TYPE 2 (R. C. P.1 CL III)
FOOT
476
100.00
$
47,600.00
10
STORM SEWERS, SPECIAL 12' (D.I.P.1CL 50)
FOOT
30
145,00
$
4,350.00
11
CATCH BASIN, TYPE A, 4' DIAMETER, TYPE 1 FRAME, OPEN LID
EACH
1
6,500.00
$
6,500.00
12
MANHOLE, TYPE A, 4' DIAMETER, TYPE 1 FRAME, OPEN LID
EACH
3
6,000.00
$
18,000.00
13
INLET, TYPE A, TYPE 1 FRAME, OPEN LID
EACH
5
2,000.00
$
10,000.00
14
MANHOLE TO BE ADJUSTED
EACH
1
550.00
$
550.00
15
COMBINATION CONCRETE CURB AND GUTTER, TYPE B 6,12
FOOT
220
30.00
$
6,600.00
16
PAVEMENT REMOVAL
SQ. YD.
65
25.00
$
1,625.00
17
DRIVEWAY PAVEMENT REMOVAL
SO. YD,
535
18.00
$
9,630.00
18
COMBINATION CURB AND GUTTER REMOVAL
FOOT
220
8.00
$
1,760,00
19
SIDEWALK REMOVAL
SO, FT.
510
2.50
$
1,275.00
20
PORTLAND CEMENT CONCRETE DRIVEWAY PAVEMENT - 6'
SO. YD.
535
68.00
$
36,380.00
21
PORTLAND CEMENT CONCRETE SIDEWALK - T
SO. FT.
510
8.00
$
4,080,00
22
PROTECTIVE SEALER
SO. YD.
2150
2.00
$
4,300.00
23
CRUSHED STONE, CA -14
TON
30
40.00
$
1,200.00
24
FURNISHING AND PLACING TOPSOIL, 3'
SO. YD.
120
8.00
$
960,00
25
SODDING, SALT TOLERANT
SO. YD.
120
15.00
$
1,800.00
26
CLASS B PATCHES, SPECIAL 9' (HES)
SO. YD.
30
110.00
$
3,300.00
27
DETECTABLE WARNINGS
SO. FT.
60
45.00
$
2,700.00
28
HOT -MIX ASPHALT SURFACE REMOVAL
SO. YD,
80
20.00
$
1,600.00
29
TEMPORARY FENCE
FOOT
120
5.00
$
600.00
BLl EST 1523
Page -2-
Estimate of Engineer of BLI - S.A. 1523
(Ailey NlPayne St., EJMcDaniel Ave.)
ITEM
UNIT
ITEM
UNIT
QUANTITY
TOTAL
CT
30
CONSTRUCTION LAYOUT AND STAKING
WM. SUM.
1
6,000.00
$
6,000.00
31
STREET SWEEPING
EACH
4
500.00
$
2000.00
32
SOIL DISPOSAL ANALYSIS
LUM. SUM.
1
3,000.00
$
3,000.00
33
NON SPECIAL/SPECIAL WASTE DISPOSAL
CU.YD
550
60.00
$
33.000.00
34
CLOSED CIRCUIT TV INSPECTION
LUM. SUM.
1
4,000.00
$
4,000.00
35
PRE -CONSTRUCTION SURFACE VIDEOTAPING
LUM. SUM.
1
2,000.00
$
2,000.00
36
TREE REMOVAL(6 TO 15 INCH DIAMETER)
UNIT.DIA..
57
50.00
$
2,850.00
37
TREE REMOVAL(OVER 15 INCH DIAMETER)
UNIT.DIA.
16
80.00
$
1,280.00
38
EPDXY PAVEMENT MARKING LINE-4' YELLOW
FOOT,
180
30.00
$
5,400.00
TOTAL
$
440,790.00
Cost of Engineering Services ......................... $ 19,835.55
For Lawful Expenses, etc ............................. $ 19,835.55
Sub -Total ....................................... $ 39,671.10
RECAPITULATION
Construction Cast ............................ $ 440,790.00
Engineering ................................... $ 19,835.55
Legal ........................................... $ 19,835.55
Total Cost ..................................... $ 480,461.10
I hereby certify that in my opinion: the above estimate does not exceed the probable cost of
the above proposed improvement and the lawful expenses attending the same.
N&Z��
-
ar N. Biggs, P.E.
City Engineer
Board of Local Improvements